The historic moving of Kiruna church, made possible by Bravida
Bravida is responsible for dismantling, preserving and preparing the
technical infrastructure for reinstallation, which will begin in 2026.
Careful dismantling
Before the move, Bravida dismantled all the technology in the church,
ranging from electrical installations to HVAC systems, with the utmost
care. The work was carefully documented and carried out in close
collaboration with Historiska Hus, Veidekke and LKAB.
In 2026, Bravida will install new technology, including new fire
alarms, access control systems, alarm systems, lighting and heating
solutions. The technology spaces are located in the new basement
level, where electricity, heating, plumbing and ventilation are brought
together to ensure modern operation while preserving the required
cultural-historical character of the building.
Reuse promotes sustainability and underpins expression
The project has imposed high requirements regarding technology and
feeling. Much of the material has been reused, both for sustainability
reasons and to preserve the original look of the building. Among other
things, various luminaires, pipes and heating elements have been
retained in the pews.